New construction paving,
sequenced so nothing gets wrecked.

The most common new-construction paving mistake isn't quality — it's timing. Pave too early and the trades destroy it; too late and closings slip. Here's the sequencing that works.

Updated July 2026 · California Asphalt Professionals · CSLB C-32 #760658 · Ballpark figures are planning aids, not quotes — the free site walk produces the real number.

When to pave in the build

Base rock early, asphalt late: install and compact the base when utilities are in — it survives construction traffic and keeps the site workable — then place the asphalt surface after heavy trades are done and before final landscaping. For driveways, that's typically after drywall and exterior paint; for subdivisions, after the last lot's heavy deliveries on that street. Concrete flatwork follows its own clock (protect it from equipment for a week).

The base-as-road trick

A properly built base doubles as the construction road for months. It costs nothing extra — you were paying for that base anyway — and it means concrete trucks, lumber deliveries and cranes never rut the subgrade they'll eventually rely on. We build it to final grade and tolerance, so paving day is paving, not repair.

Coordination items

What we need from a GC: final grades locked, utility trenches compacted to spec (a lazy trench backfill telegraphs through asphalt as a settling stripe within a year), garage slab elevations confirmed so the driveway lands flush, and a realistic weather window. What you get from us: a written section spec for the plans, scheduling that follows your critical path, and phone calls answered by the same person all build long.

Punch-list reality

New pavement takes its worst abuse in the last month of construction — movers, sod trucks, dumpster swaps. Sensible plans hold a small line for pre-closing touch-up: a scuff pass, corner repairs, final sweep-and-seal on flatwork. Cheaper as a planned item than an angry-buyer emergency.